Construction Notice - FY26 Water Main Replacement - Construction is expected to start the week of June 29th and last until the mid-September
PROJECT OVERVIEW
The City of Valley Contractor, Vrba Construction, Inc., will be replacing old water main pipes in along Reichmuth Road, Alexander Street, Charles Street, Whittingham, Lakewood, and Waring Streets as highlighted below. The Contractor will install new water main pipe, make connections to existing pipes, and connection existing residential water services. This project is part of the City’s overall plan to replace aging infrastructure, improve the water quality and provide reliable service delivery to the residents. Construction is expected to start the week of June 29th and last until the mid-September.
Construction will require portions of the streets or sidewalks to be closed but access to homes will be maintained unless directly contacted. Residents are advised to use caution throughout the construction zones and follow temporary traffic control signs throughout the construction process. We appreciate your patience and cooperation during the project.
FACTS
• Existing water main age back to the early 1900’s
• New PVC water main will replace cast iron water main
• Brief interruptions in the water service will occur. Affected residents will be notified in advance before any shut-offs occur. Unforeseen disruptions may occur, the Contractor will be on-site immediately to restore water service.
• Open cut trench and horizontal boring will be the installation techniques used on the project.
• Surface restoration, including concrete replacement and turf grass, will occur after the work is complete.
EAGLE ENGINEERING GROUP
12100 West Center Road, Suite 803
Omaha, Nebraska 68144-3970
Gregory Perry, PE, City Engineer